First stage of building of MISP «Prirazlomnaja» finished – the stage of the enterprise manufacturing. The unique platform began a movement in the direction of Murmansk.

At Murmansk ship-repair plant no.35 second stage will begin – the overbuilding and setting-arranging works. «The works at Murmansk were planned in the beginning of project, – deputy of enterprise general director, chief of the production of marine techniques and civil shipbuilding Valery Borodin said, answering the question about reasons of the platform transfer from Sevmash. – After the concreting the platform sediment will compose 19 meters. We have no such depths. Also the water area of Kolsky peninsula not freeze in winter».

«Prirazlomnaja» – the first platform in the world, designed for mastering in the region of «Prirazlomnoye» oilfield in Pechora sea. Its exceptionality in the possibility to work in extremely climatic conditions: in ice fields and at the temperature of minus 50 degrees of Celcium. The platform is intended for all the year round service boring, possess the boring arrangement, two tabs, helicopter landing site.

«We intend already in fourth quarter of next year to receive oil, – general director JSC «Gasprom oil shelf» Aleksander Mandel declared. – But we shall have to work much for it. Sevmash will conduct this project to the finish as the general running». First 100 workers are sent already on mission from Severodvinsk to Murmansk.

In favorable weather the platform transporting will occupy 6-10 days.

 

Anastasija Nikitinskaja,

chief of press-service of JSC «PO «Sevmash»